Maritime Academy

Shipboard Incinerator

Classify the waste, check location, verify the approved unit and maintain an evidence chain.

ENV-02Source review: 17 October 2026Revision 1 · Source-based reference

Read MARPOL Annex VI regulation 16 with Annex V. Unit-specific and local port requirements also apply.

Rules and bulletins may change. Before operation or voyage, verify the latest official source and ship-specific applicability. This page is not permission, certification or a real-time risk notice.

FOUR-STAGE TOPIC OVERVIEW

Establish applicability, then verify the operation

Shipboard Incinerator — schematic learning diagram
Original educational schematic, not to scale. Not an operating diagram, official area chart or ship drawing. Numbers correspond to the stages below.
  1. Identify waste

  2. Check place/prohibition

  3. Verify unit procedure

  4. Manage ash/records

1 · Classify what will be burned

Regulation 16 prohibitions include Annex I/II/III cargo residues/contaminated packaging, PCBs, garbage with more than traces of heavy metals, halogen-containing refined petroleum products, sludge/sewage sludge not generated onboard and EGCS residues. PVC requires the relevant IMO type-approval conditions. Do not feed unidentified waste.

Reference: IMO — Shipboard incineration, regulation 16 ↗

2 · Apply location restrictions precisely

Burning ship-generated sewage sludge/sludge oil in main/auxiliary power plant or boilers is prohibited within ports, harbours and estuaries. Do not misstate this as an identical blanket prohibition on every approved incinerator operation: independently verify local incinerator restrictions and permissions.

Reference: IMO — Shipboard incineration, regulation 16 ↗

3 · Follow the exact unit procedure

Match type approval, manual, training and permitted waste classes. Obtain prechecks, ventilation, auxiliary fuel, temperature/feed permissions, alarms and cooling sequence from maker procedures. Never defeat interlocks. This page is not an ignition or maintenance instruction.

Reference: IMO — Shipboard incineration, regulation 16 ↗

4 · Manage ash and records

Link incineration to appropriate Garbage Record Book/ORB entries. Do not assume ash/unburned residues may go overboard; follow waste-management and reception arrangements. Sludge quantities, tank changes and operation times must reconcile.

Reference: IMO — MARPOL Annex V, garbage and records ↗

MASTER • RESPONSIBLE OFFICER • COMPANY

Six field checks

  1. Identify waste type, origin and prohibited classes.
  2. Verify position and port/terminal restrictions.
  3. Check the approval/manual permits that waste.
  4. Complete training, alarms and prechecks under vessel procedures.
  5. Stop on deviation; segregate uncertain waste and escalate.
  6. Complete sludge/waste, ash and record/receipt chain.

Educational checklist. Completion is not operational/compliance approval; use the relevant vessel permits/forms separately.

Documents to have available

  • IMO approval and manual
  • Garbage Management Plan and GRB
  • Sludge/ORB records
  • Port instructions and ash receipts

Onboard scenarios

Plastic waste, but PVC content is unknown.

Segregate and identify it; do not feed before checking approval.

Burning sludge in a boiler while in port.

Apply the regulation 16.4 restriction; do not operate that alternative. Also verify local instructions.

LEARNING CHECK

Think of your answer, then reveal the explanation

May EGCS residues be incinerated?

No; they are included in regulation 16 prohibitions.

Do all units share temperature/feed settings?

No. Follow applicable approval conditions and maker procedures.

Self-assessment only; no exam result, personnel record or competence certificate is generated.

Open the official sources

Legal instruments, explanatory guidance and operational bulletins have different roles. Check later amendments and consolidated texts where needed. Access and external documents remain under the publisher’s control.

Related topics